top of page
Additional language translations available by request

Carlton Water Treatment Plant High-Service Pumps
Infrastructure in Sarasota County


T. Mabry Carlton Water Treatment Plant, June 3, 2025

T. Mabry Carlton Water Treatment Plant, June 3, 2025

T. Mabry Carlton Water Treatment Plant, June 3, 2025

T. Mabry Carlton Water Treatment Plant, June 3, 2025
1/3
Date Selected:
May 22, 2024
Approved Funding:
$420,000
Project Agreement:
N/A
Funds will support design and construction activities for the rehabilitation of the T. Mabry Carlton Water Treatment Plant (Carlton WTP) high-service pumps. These upgrades will enhance the plant’s reliability and capacity, ensuring its viability for future population growth, and mitigating the potential impacts of hurricanes, drought, and wildfires.
Project Location
Project Status
Timeline of Activities
✅ Step 1: Project Selected by Sarasota County Commission
Step 2: [Underway] HUD Environmental Review Process
Step 3: [Pending] Authority to use grant funds received from HUD
Step 4: [Pending] Construction / Implementation
bottom of page