121 Reconstruction
Infrastructure in City of North Port


Water Control Structure 121, Aug. 6, 2025

Water Control Structure 121, Aug. 6, 2025

Water Control Structure 121, Aug. 6, 2025

Water Control Structure 121, Aug. 6, 2025
1/3
Date Selected:
May 22, 2024
Approved Funding:
$2,042,000
Project Agreement:
Executed 7/17/25. View.
Funds will support the design and construction of a replacement for Water Control Structure 121, a four-gated structure located in North Port. This project will support approximately 15,745 citizens living in the service area.
Project Location
Project Status
Timeline of Activities
✅ Step 1: Project Selected by Sarasota County Commission
✅ Step 2: HUD Environmental Review Process
✅ Step 3: Authority to use grant funds received from HUD
✅ Step 4: Project Agreement(s) Signed
Step 5: [Pending] Construction / Implementation